JENAL Construction Diary

Enlargements of construction pictures.

CONSTRUCTION DATE
and information

PICTURE

March (early)~06

A view from the aft end forward. The engine room is on the portside (left) and the electrics room opposite starboard side (right). Martie the chief JENAL fabricator is chatting with Theo the Ament works foreman. The gap they are surveying is the March 06 problem, trying to get the multi curve of the Klipper bow to work from CAD design to real steel.

return to diary build page
 

 